The Transmission Company of Nigeria (TCN) has said power supply has been successfully restored to seven northern states聽through its 330kV Ugwuaji-Apir transmission line 1.
In a statement on Wednesday night,TCN鈥檚 General Manager of Public Affairs, Ndidi Mbah said power was restored at 4:56pm after repairs on the vandalised section of the line were completed.
She said with the restoration, the Apir-Lafia 330kV transmission line 2 is now also operational, enabling bulk power transmission to Lafia, Makurdi, Jos, Kaduna, Kano, Bauchi and Gombe.
鈥淎s restoration efforts continue, with the TCN engineering team preparing to commence work on the second 330kV transmission line, all necessary materials for the repairs are on hand, and work will begin as soon as the site is secured for the safety of our personnel to the affected sections of the vandalised 330kV transmission line 2
鈥淚n the meantime, teams of linesmen will re-patrol the 330kV line 2 to ensure that no other sections are impacted as the repair works progress.
鈥淲e appreciate your patience and understanding as our engineers work diligently to restore the 330kV transmission line 2,” She said.
Mbah said the company recognises the importance of electricity in the daily lives of Nigerians, assuring that the line will be repaired swiftly, thereby increasing the bulk power to areas affected by the incident.
TCN had on October 22聽reported聽a power outage in the North East, North West and parts of North Central after 330-kilovolt (kV) Ugwaji鈥揂pir double circuit transmission lines 1 and 2 tripped.
Two days later, Mbah said the聽faulty area, which measures one span, was identified as a snapped 330kV transmission line in the swampy forest of Igumale, Benue State.
However, on October 28, the commission said聽insecurity delayed repairs, but it is working tirelessly to restore power supply.