Akinwande Soji-Ojo
Minister of Power, Chief Adebayo Adelabu, has expressed concern over what he described as the politicisation of technical challenges in the power sector, rejecting allegations of incompetence levelled against him by members of the Oyo State House of Assembly.
In a statement issued by his Special Adviser on Strategic Communications and Media Relations, Bolaji Tunji, the minister clarified that the transmission challenges affecting Ibarapa predate the current administration.
According to Tunji, the issues were largely caused by funding shortfalls and unresolved compensation matters linked to critical infrastructure belonging to the Transmission Company of Nigeria (TCN).
“The politicisation of largely technical matters is regrettable,� the statement said.
He urged the lawmakers to prioritise constructive engagement and collaboration between federal and state authorities to improve electricity supply in Oyo State.
Tunji advised the assembly to focus on its constitutional responsibilities, particularly in light of recent amendments that placed electricity on the Concurrent Legislative List, thereby empowering states to generate, transmit and distribute power within their jurisdictions.
“While several states have taken advantage of these provisions to establish independent power initiatives, Oyo State has yet to fully utilise the opportunities available to complement federal efforts,� he said.
The statement also questioned why the assembly did not hold the state government accountable for the unsuccessful Independent Power Project undertaken with Elektron Energy, despite significant public investment. It noted that the contractor reportedly suspended services due to persistent non-payment.
Tunji further expressed concern that the assembly was raising the issues after nearly seven years in office and less than a year to the next general elections.
“The action appears politically motivated and aimed at discrediting the minister rather than addressing genuine service delivery concerns,� the statement added.
Tunji confirmed that concrete steps are being taken to restore stable electricity supply to Ibarapaland. He explained that the major delay in the transmission project was linked to the non-release of funds for compensation to affected landowners, an issue that arose before the current minister assumed office.
“Contractors are currently on site to assess affected properties and commence compensation payments, thereby enabling full-scale project implementation. All essential equipment for the project is already in place
“Previously abandoned and vandalised TCN facilities in the area are being rehabilitated, while electricity supply has been restored to Ibarapa Central after prolonged outages. In addition, street lighting projects have been implemented in several communities to improve security and promote economic activity,� he added.
Tunji further explained that last-mile electricity distribution in Oyo State, including Ibarapa, falls under the responsibility of the Ibadan Electricity Distribution Company (IBEDC), which oversees feeders, transformers, metering and billing.
He maintained that the ministry continues to engage IBEDC to enhance service delivery and address issues related to estimated billing in line with regulatory standards, as demonstrated by the Adelabu’s recent visit to the company.
Residents of Ibarapaland were assured that, with the compensation process underway and equipment already procured, tangible progress on the transmission project would soon result in improved power supply across the zone.
Tunji noted that Oyo State has received significant attention in the power sector under the current administration.
Among key completed and ongoing projects listed are the construction and commissioning of 132/33kV mobile substations at Ajibode (University of Ibadan axis) and Eleyele-Sango by FGN Power Company; the upgrade of the Ayede Ring Road 330/133kV substation under the Presidential Power Initiative in partnership with Siemens; approval and construction of new substations at New Asejire and Lalupon/Ejioku; and a 15MW solar interconnected grid for the University of Ibadan and the University College Hospital by the Rural Electrification Agency.
Other projects include the capacity upgrade of the Jericho 133/32kV substation; concessioning of the Ikere Gorge Dam to boost generation by 20MW; completion of 33kV lines from Iseyin to Okeho; construction of a new 133/32kV substation in Saki; rehabilitation of substations in Igbo-Ora and Lanlate; installation of solar mini-grids in rural communities; and approval of highway lighting for the Lagos–Ibadan Expressway.
Tunji urged the state government and the House of Assembly to complement Federal Government’s initiatives, noting that collaboration remains key to achieving sustainable electricity supply and economic development in Oyo State.