By Emmanuel Adeleke
The Chief Executive Officer(CEO) of the Nigerian National Petroleum Company Limited (NNPCL), Bayo Ojulari, has explained that Nigeria鈥檚 state-owned refineries failed to function effectively because past efforts focused mainly on financing and engineering, procurement and construction (EPC), rather than on long-term operations.
Ojulari spoke at the just-concluded Nigerian International Energy Summit (NIES), where he said the refineries were built without adequate attention to how they would be sustainably operated.
鈥淭he reason our refineries have not worked is that we focused on the first two 鈥� EPC and financing. Anyone who wants to do the financing will get value for it.
鈥淭he person financing is not financing you for free. They are financing for margins and profitability. The EPC contractors do their work, get paid, and move on.
鈥淵ou, as NNPCL, are then left for the next 20 to 40 years to run those refineries, and we鈥檝e never really focused on that,鈥� he stated.
Ojulari said there had been extensive discussions around Operations and Maintenance (O&M), noting that globally, effective O&M requires a strong operational excellence team to oversee the process.
According to him, without such a team, resources are often wasted.
鈥淥&M is another contract. So you end up with financing, EPC, and O&M 鈥� all of them taking money from the system without any skin in the game.
鈥淭here鈥檚 no way you can sustain any business like that. It鈥檚 very clear. The system was designed for taking, not for putting anything in,鈥� he said.
Ojulari explained that the current NNPCL leadership has decided to focus on 鈥渢hat part that has been missing.鈥�
鈥淔or those of us who have spent years building multi-billion-dollar facilities for international oil companies, we understand these principles. From the day you start a project, you appoint an operational assurance person who is involved from the outset to ensure that what is delivered can actually be operated,鈥� he said.
The NNPCL CEO recalled his experience working at Shell, where he served on the commissioning team for the Qatargas project.
鈥淔rom the beginning, during the project phase, I was part of the operations readiness team. Long before the gas plants were constructed, we conducted audits on operational readiness.
鈥淭he first audit was done before construction, and the second was carried out when construction was about 90 per cent completed,鈥� Ojulari said.
He noted that issues identified during these audits explained why operability would have been a challenge if they were not addressed.
鈥淭hen you build the capability, training, and resources required to operate the facility. For most mega-projects, you spend two to three years conceptualising and framing the project, three to five years constructing it, and about 25 to 50 years operating it.
鈥淪o where should your focus be?鈥� he asked.
Ojulari added that NNPCL had previously handled these critical issues with kid gloves.
He also disclosed that the company is currently discussing a potential partnership with a Chinese firm over one of the state-owned refineries.