By Efa Sunday
The Nigerian Electricity Regulatory Commission (NERC) has issued a new directive requiring detailed regional reporting of transmission losses, setting a tougher target for the Transmission Company of Nigeria (TCN) as part of efforts to improve grid performance and accountability.
NERC, in a memo dated April 8, instructed TCN to ensure that transmission losses across all regions do not exceed 6.5 per cent by the end of 2026.
The order, which takes effect Monday, is anchored on provisions of the Electricity Act 2023.
Under the new framework, the Nigerian Independent System Operator (NISO) will play a central role in monitoring and reporting energy flows across the grid. The operator is expected to deploy smart meters at all regional interconnection points before December 2026 to enable precise measurement of electricity transmitted between regions.
In addition, NISO is mandated to monitor energy passing through transmission transformers and submit quarterly reports detailing regional performance to the commission.
Available data show that while transmission losses have declined in recent years, they remain above regulatory limits. Figures from the system operator indicate that the national transmission loss factor dropped from 8.71 per cent in 2024 to 7.24 per cent in 2025, with recent improvements bringing it closer to 7.05 per cent. However, these levels still exceed the seven per cent benchmark set under the Multi-Year Tariff Order.
To meet the new requirement, TCN has been directed to present a comprehensive compliance plan by July 2026, outlining strategies to achieve the revised threshold. By the end of December 2026, each transmission region is expected to operate within the 6.5 per cent cap.
The order follows growing concern over the financial burden of transmission inefficiencies on the power sector.
The Managing Director of NISO, Abdu Mohammed Bello, had earlier disclosed that losses initially cost the sector between N5 billion and N8 billion monthly, with loss levels once approaching 10 per cent.
He noted that recent operational improvements have helped reduce losses, but further reductions to between five and six per cent are necessary to align with regulatory expectations.
The directive is part of broader structural reforms in the electricity industry. The unbundling of TCN under the Electricity Act led to the establishment of NISO in 2025, separating system operations from transmission infrastructure management.
Despite some progress, the national grid continues to face reliability issues, with multiple collapses recorded in early 2026. Although peak transmission rose to 5,801.84 megawatts in March 2025, supply remains constrained by persistent challenges across the value chain.
Industry analysts believe the shift to region-based performance monitoring will enhance transparency and enforce stricter compliance, marking a more assertive regulatory approach after years of missed targets.
They also note that achieving the new benchmark will depend on sustained investment in modern grid management systems, including supervisory control and data acquisition technology, as well as improved operational efficiency.
In recent years, TCN has undertaken several infrastructure upgrades, including the installation of new transformers and the rehabilitation of transmission lines, supported by development partners such as the African Development Bank (AfDB).